GAZETTE NOTICE No. 281

THE ENERGY ACT

(No. 12 of 2006)

SCHEDULE OF TARIFFS FOR SUPPLY OF ELECTRICAL ENERGY BY THE KENYA POWER AND LIGHTING COMPANY LIMITED

NOTICE is given that pursuant to section 45 of the Energy Act, 2006, the Commission prescribes the tariffs, charges, prices and rates to be charged to the Kenya Power and Lighting Company Limited by consumers for electrical energy consumed by them as set out in the Schedule.

SCHEDULE

PART I—PRELIMINARY

  1. (1) This Schedule shall take effect on the date of publication.

 

(2)  The Schedule shall take effect -

 

(a)     with respect to a post-paid consumers for bills raised based on meter readings taken on or after the effective date; and

 

(b)     with respect to pre-paid consumers for Units purchased on or after the effective date.

(3) Subject to sub-paragraph (2), the tariffs set out in Part II-

(a)      paragraph 3 shall take effect on the date of publication of this Schedule;

(b)      paragraph 4 shall take effect on 1st July, 2014; and

(c)      paragraph 5 shall take effect on 1st July, 2015.

  1. In this Schedule unless the context otherwise requires –

 

“Company” means the Kenya Power and Lighting Company Limited;

 

“consumer” means any person who is supplied with electrical energy, but does not include a person who is supplied with electrical energy for delivery or supply to another person;

 

“contract” means an agreement made between a consumer and the Company for supply of electrical energy, which is in force as at the date of commencement of this Schedule of Tariffs and includes all contracts entered into with consumers after this date;

 

“demand” means the maximum electric power demand drawn by a consumer during each post-paid billing period;

 

“demand charge” means a charge for demand supplied per kVa in each post-paid billing period, when applicable, with respect to the consumer category set out in Part II of the Schedule;

 

“electric power producer” means a person who owns or operates facilities for generation of electrical energy pursuant to a generating licence issued by the Commission;

 

“energy charge” means a charge per Unit consumed in each post-paid billing period or per Unit purchased in each pre-paid units purchase period, as the case may be, with respect to each consumer category as set in Part II;

 

“fixed charge” means the amount charged per post-paid billing period or pre-paid units purchase period, with respect to each consumer category as shown in Part II;

 

“Interconnected System” means works inclusive of power stations, electric supply lines electrically interconnected forming the main supply grid in the Republic of Kenya;

 

“KenGen” means the Kenya Electricity Generating Company Limited;

 

“kVA”  means kilovolt Ampere;

 

“meter” means any kind of machine, device or instrument used for the measurement of the quantity of electrical energy, and includes such auxiliary appliances such as resistors, shunts, reactance, current  transformers, voltage transformers and time switches, external and necessary to the meter;

 

“Off-Grid System” means works inclusive of power stations and electrical supply lines which are electrically and physically separate from the Interconnected System;

 

“post-paid billing period” means the period of time elapsing between the issuing of two consecutive bills by the Company, but with the exception of their first and last period, such period of time shall be as near to thirty days as possible;

 

“post- paid consumer” means a consumer who consumes electricity on credit and pays for it after receiving a bill from the Company in accordance to the terms and condition of supply;

 

“power factor” means the decimal fraction obtained by dividing the demand in kilowatts by the demand in kiloVolt amperes and shall be ascertained by suitable apparatus installed by the Company;

 

“pre-paid consumer” means a consumer who pays for electricity up-front, either by purchasing a top-up card or tokens from the Company  or its agent in accordance to the terms and condition of supply  and uses it to load Units to his or her pre-paid meter;

 

“pre-paid unit purchase period” means a calendar month;

 

“tariff” means the prices, rates, costs and all other charges including adjustments, formulae and other terms, conditions and information contained in parts II, III and IV of this Schedule ;

 

“Unit” means one kiloWatt hour (kWh);

 

“units purchased” means electricity measured in kWh generated by the Company’s power plants or electric power producers power plants delivered to and purchased by the Company.

 

PART II- NON-FUEL TARIFFS FOR ELECTRICAL ENERGY SUPPLIED BY THE COMPANY

 

  1. The tariffs to be applied by the Company for the supply of electrical energy from the Interconnected System and also from the Off-Grid Systems, in each post-paid billing period or pre-paid units purchase period shall be as set out in the table below-

 

Method

Tariff

METHOD DC

(1)         This method shall apply to domestic consumers for supply provided and metered by the Company at 240 or 415 volts and whose consumption does not exceed 15,000 Units per post-paid billing period or pre-paid units purchase period and the tariff payable shall be –

 

(a)          a fixed charge of Ksh 120.00;

 

(b)         an energy charge of –

 

                        (i)        Ksh 2.50 per Unit for 0 - 50 Units consumed;

                       (ii)        Ksh 11.62 per Unit for 51-1,500 Units consumed; or

                     (iii)        Ksh 19.57 per Unit for Units consumed above 1,500.

(2)         If Method DC is used in conjunction with Method IT at the same supply terminals, then the combined fixed charge for both methods of charge shall be Ksh 240.00 with respect to pre-paid consumer, this amount shall be charged on Method DC.

 

METHOD SC

(1)         This method shall apply to non-domestic small commercial consumers for supply provided and metered by the Company at 240 or 415 volts and whose consumption does not exceed 15,000 Units per post-paid billing period or pre-paid units purchase period and the tariff payable shall be –

(a)   a fixed charge of Ksh 150.00*; or

 

(b)   an energy charge of Ksh 12.00 per Unit for all Units consumed.

 

(2)         If Method SC is used in conjunction with Method IT at the same supply terminals, then the combined fixed charge for both methods of charge shall be Ksh 270.00.

 

(3)         With respect to a pre-paid consumer, this amount shall be charged on Method SC.

 

METHOD CI1

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 415 volts three phase four-wire and whose consumption exceeds 15,000 Units per post-paid billing period and the tariff payable shall be –

 

(a)   a fixed charge of Ksh 2,000.00;

 

(b)   an energy charge of Ksh 8.70 per Unit consumed; or

 

(c)   a demand charge of Ksh 800.00 per kVA.

 

METHOD CI2

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 11,000 volts, per post-paid billing period and the tariff payable shall be -

(a)   a fixed charge of Ksh 4,500.00;

(b)   an energy charge of Ksh 7.50 per Unit consumed; or

(c)   a demand charge of Ksh 520.00 per kVA.

METHOD CI3

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 33,000 volts, per post-paid billing period and the tariff payable shall be -

(a)   a fixed charge of Ksh. 5,500.00;

(b)   an energy charge of Ksh 7.00 per Unit consumed; or

(c)   a demand charge of Ksh 270.00 per kVA.

METHOD CI4

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 66,000 volts, per post-paid billing period and the tariff payable shall be -

(a)   a fixed charge of Ksh 6,500.00;

(b)   an energy charge of Ksh 6.80 per Unit consumed; or

(c)   a demand charge of Ksh 220.00 per kVA.

METHOD CI5

This method shall apply to commercial and industrial consumers for supply provided and metered by the company at 132,000 volts, per post-paid billing period and the tariff payable shall be -

(a)   a fixed charge of Ksh 17,000;

(b)   an energy charge of Ksh 6.60 per Unit consumed; or

(c)   a demand charge of Ksh 220.00 per kVA.

METHOD IT

(1)         This method shall apply for interruptible off-peak supply of electrical energy applicable to ordinary consumers provided and metered by the Company whose consumption does not exceed 15,000 Units per post-paid billing period or pre-paid units purchase period and the tariff payable shall be -

(a)   a fixed charge of Ksh 120.00*; or

(b)   an energy charge of Ksh 13.00 per Unit consumed.

(2)         If Method IT is used in conjunction with Method DC or Method SC at the same supply terminals, then the combined fixed charge for both methods of charge shall be Ksh 240.00 or Ksh.270 respectively. For Pre-paid Consumers the applicable combined fixed charge will be charged on DC or SC meter.

Notes:

Note 1: The electrical energy which shall be supplied and charged under this method of charge shall be available at all times other than during peak periods which shall be such periods of high demand as may occur during each day not exceeding sixteen hours in the aggregate and during which the supply of electrical energy may be restricted, the time or times of such restriction and the duration thereof being controlled by the Company at its sole discretion.

Note 2: This tariff shall apply to installations arranged to the Company's satisfaction such that they cannot be operated on any other tariff and also where there is no duplication of the off-peak circuits by other electrical circuits unrestricted as to time of use so enabling the supply on another method of charge to be used for a similar function.

Note 3:               The Company shall provide and maintain apparatus up to a maximum capacity of 15 amperes, single phase, to control the period of availability of the supply and shall take all reasonable steps to ensure the reliability thereof, but shall not be responsible for any loss, damage or injury which may result from any mal-operation of this control equipment.

METHOD SL

(1)         This method shall apply to public corporations and county governments metered by the Company at 240 or 415 volts per post-paid billing period for supply of electrical energy to public lamps which includes Street Lighting and the tariff payable shall be -

(a)   a fixed charge of Ksh 200.00; or

(b)   an energy charge of Ksh 10.50 per Unit consumed.

(2)         Supply under this method of charge shall be available for a minimum period of 11 hours per night for public lamps and for no other purpose.

(3)         The attention of public corporation and county governments taking supply on this tariff is drawn to the fact that where public lamps are fitted on the Company's poles, all maintenance of the lamps, switch wire and associated equipment must be carried out by the Company and shall be charged for on the basis of net costs of materials, labour and transport plus 25%.

Note: Every consumer shall pay to the Company a fixed charge at a rate not exceeding Ksh 50.00 per kVA per post-paid billing period or pre-paid units purchase period of name plate kVA continuous rating in respect of all electric welding plant, as adjusted by any power factor equipment in use in addition to the charges specified in Part II of this Schedule.

 

  1. The tariffs to be applied by the Company for the supplies of electrical energy from the Interconnected System and the Off-Grid Systems, in each Post-paid Billing Period or Pre-paid Units Purchase Period shall be as set out in the table below-

 

Method

Tariff

METHOD DC

(1)         This method shall apply to domestic consumers for supply provided and metered by the Company at 240 or 415 volts and whose consumption does not exceed 15,000 Units per Post-paid Billing Period or Pre-paid Units Purchase Period and the tariff payable shall be-

(a)      a fixed charge of Ksh 150.00*; or

(b)      an energy charge of -

                       (i)        Ksh 2.50 per Unit for 0 - 50 Units consumed;

                      (ii)        Ksh 13.68 per Unit for 51-1,500 Units consumed; or

                    (iii)        Ksh 21.57 per Unit for Units consumed above 1,500.

(2)         If Method DC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be Ksh 300.00.

(3) With respect to Pre-paid Consumer, this amount shall be charged on method DC.

METHOD SC

(1)         This method shall apply to non-domestic small commercial consumers for supply provided and metered by the Company at 240 or 415 volts and whose consumption does not exceed 15,000 Units per post-paid billing period or pre-paid units purchase period  and the tariff payable shall be -

(a)      a fixed charge of Ksh 150.00*; or

(b)      an energy charge of Ksh 14.00 per Unit for all Units consumed.

(2)         If Method SC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both methods of charge shall be Ksh 300.00.

(3)         With respect to Pre-paid Consumer, this amount shall be charged on Method SC.

METHOD CI1

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 415 volts three phase four-wire and whose consumption exceeds 15,000 Units per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 2,000.00;

(b)         an energy charge of Ksh 9.45 per Unit consumed; or

(c)          a demand charge of Ksh 800.00 per kVA.       

METHOD CI2

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 11,000 volts, per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 4,500.00;

(b)          an energy charge of Ksh 8.25 per Unit consumed; or

(c)          a demand charge of Ksh 520.00 per kVA.

METHOD CI3

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 33,000 volts, per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 5,500.00;

(b)          an energy charge of Ksh 7.75 per Unit consumed; or

(c)          a demand charge of Ksh 270.00 per kVA.

METHOD CI4

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 66,000 volts, per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 6,500.00;

(b)          an energy charge of Ksh 7.55 per Unit consumed;

(c)          a demand charge of Ksh 220.00 per kVA.

METHOD CI5

This method shall apply by commercial and industrial consumers for supply provided and metered by the Company at 132,000 volts, per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 17,000;

(b)          an energy charge of Ksh 7.35 per Unit consumed; or

(c)          a demand charge of Ksh 220.00 per kVA.

METHOD IT

(1)         This method shall apply for interruptible off-peak supply of electrical energy applicable to ordinary consumers provided and metered by the Company whose consumption does not exceed 15,000 Units per post-paid billing period or pre-paid units purchase period and the tariff payable shall be -

(a)          a fixed charge of Ksh 150.00* ; or

(b)          an energy charge of Ksh 13.75 per Unit consumed.

(2)         If Method IT is used in conjunction with Method DC or Method SC at the same supply terminals, then the combined fixed charge for both methods of charge shall be Ksh 300.00.

(3)         For pre-paid consumers the applicable combined fixed charge will be charged on DC or SC meter.

Notes:

Note 1                : The electrical energy which shall be supplied and charged under this method of charge shall be available at all times other than during peak periods which shall be such periods of high demand as may occur during each day not exceeding sixteen hours in the aggregate and during which the supply of electrical energy may be restricted, the time or times of such restriction and the duration thereof being controlled by the Company at its sole discretion.

Note 2: This tariff is only available for installations arranged to the Company's satisfaction such that they cannot be operated on any other tariff and also where there is no duplication of the off-peak circuits by other electrical circuits unrestricted as to time of use so enabling the supply on another method of charge to be used for a similar function.

Note 3:   The Company shall provide and maintain apparatus up to a maximum capacity of 15 amperes, single phase, to control the period of availability of the supply and shall take all reasonable steps to ensure the reliability thereof, but shall not be responsible for any loss, damage or injury which may result from any mal-operation of this control equipment.

METHOD SL

(1)         This method shall apply to public and county governments metered by the Company at 240 or 415 volts per post-paid billing period for supplies of electrical energy to public lamps  including Street Lighting and the tariff payable shall be -

(a)          a fixed charge of Ksh 200.00;

(b)          an energy charge of Ksh 11.25 per Unit consumed.

(2)         Supply under this Method of Charge shall be available for a minimum period of 11 hours per night for public lamps and for no other purpose.

(3)         The attention of public corporation and County Governments taking supply on this tariff is drawn to the fact that where public lamps are fitted on the Company's poles, all maintenance of the lamps, switch wire and associated equipment must be carried out by the Company, and shall be charged for on the basis of net costs of materials, labour and transport plus 25%.

Note:

Every consumer shall pay to the Company a fixed charge at a rate not exceeding Ksh 50.00 per kVA per post-paid billing period or pre-paid units purchase period of name plate kVA continuous rating in respect of all electric welding plant, as adjusted by any power factor equipment in use in addition to the charges specified in Part II of this Schedule.

 

  1. The tariffs to be applied by the Company for the supply of electrical energy from the Interconnected System and also from the Off-Grid Systems, in each post-paid billing period or pre-paid units purchase period shall be as set out in the table below-

 

Method

Tariff

METHOD DC

This method shall apply to domestic consumers for supply provided and metered by the Company at 240 or 415 volts and whose consumption does not exceed 15,000 Units per post-paid billing period or pre-paid units purchase period and the tariff payable shall be -

(a)          a fixed charge of Ksh 150.00*;

(b)         an energy charge of-

                       (i)        Ksh 2.50 per Unit for 0 - 50 Units consumed;

                      (ii)        Ksh 12.75 per Unit for 51-1,500 Units consumed; or

                    (iii)        Ksh 20.57 per Unit for Units consumed above 1,500.

(2) If Method DC is used in conjunction with Method IT at the same supply terminals, then the combined fixed charge for both methods of charge shall be Ksh 300.00.

(3) With respect to pre-paid consumers, this amount shall be charged on Method DC.

METHOD SC

(1) This method shall apply to non-domestic small commercial consumers for supply provided and metered by the Company at 240 or 415 volts and whose consumption does not exceed 15,000 Units per post-paid billing period or pre-paid units purchase period and the tariff payable shall be -

(a)          a fixed charge of Ksh 150.00*;

(b)          an energy charge of Ksh 13.50 per Unit for all Units consumed.

(2) If Method SC is used in conjunction with Method IT at the same supply terminals, then the combined fixed charge for both methods of charge shall be Ksh 300.00.

(3) With respect to pre-paid consumer, this amount shall be charged on Method SC.

 

METHOD CI1

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 415 volts three phase four-wire and whose consumption exceeds 15,000 Units per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 2,500.00;

(b)         an energy charge of Ksh 9.20 per Unit consumed;

(c)          a demand charge of Ksh 800.00 per kVA.

METHOD CI2

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 11,000 volts per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 4,500.00;

(b)          an energy charge of Ksh 8.00 per Unit consumed; or

(c)          a demand charge of Ksh 520.00 per kVA.

METHOD CI3

This method shall apply to commercial and industrial Consumers for supply provided and metered by the Company at 33,000 volts per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 5,500.00;

(b)          an energy charge of Ksh 7.50 per Unit consumed; and

(c)          a demand charge of Ksh 270.00 per kVA.

METHOD CI4

This method shall apply to Commercial and Industrial Consumers for supply provided and metered by the Company at 66,000 volts per post-paid billing period and the tariff payable shall be -

(a)          a fixed charge of Ksh 6,500.00;

(b)          an energy charge of Ksh 7.30 per Unit consumed; or

(c)          a demand charge of Ksh 220.00 per kVA.

METHOD CI5

This method shall apply to commercial and industrial consumers for supply provided and metered by the Company at 132,000 volts post-paid billing period and the tariff payable shall be-

(a)          a fixed charge of Ksh 17,000;

(b)         an energy charge of Ksh 7.10 per Unit consumed; or

(c)          a demand charge of Ksh 220.00 per kVA.

                    

METHOD IT

Note 1: The electrical energy which shall be supplied and charged under this method of charge shall be available at all times other than during peak periods which shall be such periods of high demand as may occur during each day not exceeding sixteen hours in the aggregate and during which the supply of electrical energy may be restricted, the time or times of such restriction and the duration thereof being controlled by the Company at its sole discretion.

Note 2: This tariff is only available for installations arranged to the Company's satisfaction such that they cannot be operated on any other tariff and also where there is no duplication of the off-peak circuits by other electrical circuits unrestricted as to time of use so enabling the supply on another method of charge to be used for a similar function.

Note 3:               The Company shall provide and maintain apparatus up to a maximum capacity of 15 amperes, single phase, to control the period of availability of the supply and shall take all reasonable steps to ensure the reliability thereof, but shall not be responsible for any loss, damage or injury which may result from any mal-operation of this control equipment.

 

 

 

METHOD SL

(1) This method shall apply to public corporation and County Governments metered by the Company at 240 or 415 volts for supply of electrical energy to public lamps  including Street Lighting and the tariff payable shall be -

(a)          a fixed charge of Ksh 200.00; or

(b)         an energy charge of Ksh 11.00 per Unit consumed.

(2) Supply under this method of charge shall be available for a minimum period of 11 hours per night for public lamps and for no other purpose.

(3) The attention of public corporation and County Governments taking supply on this tariff is drawn to the fact that where public lamps are fitted on the Company's poles, all maintenance of the lamps, switch wire and associated equipment must be carried out by the Company, and shall be charged for on the basis of net costs of materials, labour and transport plus 25%.

Note:

Every consumer shall pay to the Company a fixed charge at a rate not exceeding Ksh 50.00 per kVA per post-paid billing period or pre-paid units purchase period of nameplate kVA continuous rating in respect of all electric welding plant, as adjusted by any power factor equipment in use in addition to the charges specified in Part II of this Schedule.

 PART III- OTHER CHARGES

  1. Fuel Cost Charge

(1)                 All units billed to each Post-paid Consumer or purchased by each Pre-paid Consumer every month shall be liable to Fuel Cost Charge which shall be calculated in accordance with the following formula:

Fuel Cost Charge in Kenya cents/Unit calculated to the nearest one cent:

 

 

Where:

Ci  =         Actual price in KSh/kg paid by the Company or Electric Power Producers for fuel consumed by Plant i, where i= 1, 2, … n, during the calendar month immediately preceding each Post-paid Billing Period or Pre-paid Units Purchase Period at all existing thermal plants on the Interconnected System and the Off-Grid System, as the case may be. This shall also include other thermal power plants to be constructed and in respect of which the Company shall enter into Power Purchase Agreements.

 

Gi=          All Units generated and or purchased by the Company from Electric Power Producers’ Plant i, where i= 1, 2, …, n, during the calendar month immediately preceding each Post-paid Billing Period or Pre-paid Units Purchase Period at each existing thermal plant on the Interconnected System and the Off-Grid System, and imports/exports from Uganda Electricity Transmission Company Limited adjusted for system losses as the case may be.  This shall also include other thermal power plant(s) to be constructed and in respect of which the Company shall enter into Power Purchase Agreement(s).

 

G=           Total of all Units purchased by the Company from Electric Power Producer(s), generated by the Company and net imports during the calendar month immediately preceding each meter reading period, including all hydro stations, Off-Grid power stations and imports.

 

Si =          Specific fuel consumption in kg/Unit for the following thermal plants:

 

Embakasi Gas Turbine I & II                                            0.315 kg/Unit purchased

Kipevu I Diesel Plant                                                              0.217 kg/Unit purchased

Kipevu II Diesel Plant (Tsavo)                                          0.219 kg/Unit purchased

Kipevu III Diesel Plant                                                                            0.2095 kg/Unit purchased

Iberafrica Diesel Plants:

Old Plant                                                                            0.226 kg/Unit purchased

                                New Plant                                                                                0.224 kg/Unit purchased

Rabai Diesel Plant*:

           With steam turbine or above 33MW                                  0.1971 kg/Unit purchased

 Without steam turbine or below 33MW                                  0.208 kg/Unit purchased

Triumph Diesel Plant**                                         

           With steam turbine or above 35MW                                   0.201 kg/Unit purchased

Without steam turbine or below 35MW                             0.210 kg/Unit purchased

Gulf Diesel Plant                                                                0.215 kg/Unit purchased

Garissa Diesel Plant                                                                0.220 kg/Unit purchased

Thika Diesel Plant                    

         With steam turbine or above 33MW                                         0.199 kg/Unit purchased

 Without steam turbine or below 33MW                                  0.215 kg/Unit purchased

  Temporary Power Plants                                                  0.223 kg/Unit purchased

               

Diesel Plants in Off-Grid System***                      

Garissa                                                               0.278 kg/Unit purchased

Lamu                                                                  0.280 kg/Unit purchased

Lodwar                                                               0.282 kg/Unit generated

Mandera                                                             0.266 kg/Unit generated

Marsabit                                                             0.290 kg/Unit generated

Wajir                                                                  0.260 kg/Unit generated

Moyale                                                               0.277 kg/Unit generated

Mpeketoni                                                          0.290 kg/Unit generated

Habaswein                                                          0.290 kg/Unit generated

Hola                                                                         0.290 kg/Unit generated

Merti                                                                                       0.290 kg/Unit generated

Elwak                                                                 0.290 kg/Unit generated

Mfangano                                                           0.290 kg/Unit generated

Baragoi                                                                0.290 kg/Unit generated

Lokichogio                                                          0.290 kg/Unit generated

Takaba                                                                0.290 kg/Unit generated

Eldas                                                                   0.290 kg/Unit generated

Rhamu                                                                0.290 kg/Unit generated

 

*Rabai: The higher specific fuel consumption for Rabai Diesel Plant also applies for a period of 2.5 hours during start up after a plant shutdown of more than 8 hours.

 

**Triumph: The higher specific fuel consumption for Triumph Diesel Plant also applies for a period of 2.5 hours during start up after a plant shutdown of more than 8 hours.

 

*** Specific fuel consumption for Off-Grid System shall be estimated at 0.290 kg/unit for any other thermal power plants to be constructed for the supply of electricity to the Company from that Power Station with the approval of the Commission.

 

Pim = Sum of fuel costs for imported units calculated based on respective power import contracts.

 

Pxp = Sum of fuel costs for exported units calculated based on respective power export contracts.  

 

Pi =     Sum of fuel displacement costs and other pass through charges based on power purchased from Power Plant i, where i =1, 2 ... n. This refers to Mumias, future temporary power plants, geothermal steam charge as approved by the Commission and other power plants to be constructed in respect of which the Company shall enter into a Power Purchase Agreement.

 

i)               The fuel displacement costs, Pi, for the Mumias Power Plant shall be computed using the formula Pi = Gi×DCRi.

 

Where;

Gi =     Units purchased by the Company from the plant during the calendar month immediately preceding each Post-paid Billing Period and/or Pre-paid Units Purchase Period,

DCRi = the approved Displacement Charge Rate for the plant being US$ 0.034/kWh.

 

ii)             The fuel displacement costs, Pi, for the geothermal steam shall be computed using the formula Pi = Gi×DCRi.

 

 

 

Where;

 

Gi =     Units purchased by the Company from the plant during the calendar month immediately preceding each Post-paid Billing Period and/or Pre-paid Units Purchase Period,

DCRi = the approved Charge Rate for the plant being US$ 0.02/kWh or any other rate approved by the Commission.

 

iii)            The fuel displacement costs, Pi, for the Aeolus, Kipeto and Prunus Power Plants shall be computed using the formula Pi = Gi×DCRi.

 

            Where;

Gi =     Units generated delivered and purchased  by the Company from the plant or Units curtailed from being generated by such plant as invoiced to  the Company  in accordance with the Power Purchase Agreement  for such   plant,  during the calendar month immediately preceding each Post-paid Billing Period and/or Pre-paid Units Purchase Period,

DCRi = The approved Displacement Charge Rate for the plant being US$ 0.084/kWh.

 

iv)            The fuel displacement costs, Pi, for Power Plant plants procured through the FiT Policy shall be computed using the formula Pi = Gi×DCRi.

 

            Where;

            Gi = Units generated,  delivered  and  purchased by the Company from the plant or Units curtailed from being generated by such plant as invoiced to  the Company  in accordance with the Power Purchase Agreement  for such   plant, during the calendar month immediately preceding each Post-paid Billing Period or  Pre-paid Units Purchase Period,

 

            DCRi = The approved Displacement Charge Rate for the plant being 85%  and 70%  of  the applicable FiT tariff for Solar based plants and all other plants, respectively.

 

All fuel displacement and pass through costs shall be converted to Kenya Shillings using the CBK mean exchange rate of the calendar month immediately preceding each Post-paid Billing Period.  

 

L =           Target System loss factor in transmission and distribution equal to

 16.8% in year 2013/14, 16.6% in year 2014/15 and 15.9% in year 2015/16.

(2)   The Company shall publish a monthly notice in the Kenya Gazette showing the Fuel Cost Charge rate applicable to all Units billed to every Post-paid Consumer or Units Sold with respect to Pre-paid Consumers during the month of publication of such notice. 

 

  1. Foreign Exchange Rate Fluctuation Adjustment

(1)      All units billed to each post-paid consumer or purchased by each pre-paid consumer every month shall be liable to Foreign Exchange Rate Fluctuation Adjustment which shall be calculated in accordance with the following formula:

 

Foreign Exchange Rate Fluctuation Adjustment in Kenya cents/Unit calculated to the nearest one cent

 

 

 

 

                                  =                      ×{

 

 

}×100

 

                      Where:

 

                         = Sum of the foreign currency costs incurred by KenGen in the calendar month immediately preceding current Post-paid Billing Period or Pre-paid Units Purchase Period.

                            = Sum of the foreign currency costs incurred by the Company other than those costs relating to Electric Power Producers in the calendar month immediately preceding current Post-paid Billing Period or Pre-paid Units Purchase Period.

                               = Sum of the foreign currency costs paid by the Company to Electric Power Producers (except KenGen) in the calendar month immediately preceding current Post-paid Billing Period or Pre-paid Units Purchase Period.

 

The factor Zt is the proportionate change in the exchange rate (Xt) in the current Post-paid Billing Period or Pre-paid Units Purchase Period t from the Base Exchange rate (Xo) in the base period and shall be determined according to the following formula:

 

Zt= 

                       

 

 

Where:

 

           =      CBK mean exchange rate for the calendar month immediately preceding current Post-paid Billing Period or Pre-paid Units Purchase Period.

 

          = CBK mean exchange rate as tabulated below;

 

 

                                        CBK Mean Exchange Rates

 

Foreign Currency                                     September 2012

US Dollar                                                 84.6133

STG Pound                                              136.2555

Euro                                                        108.7977

SA Rand                                                  10.2256

AE Dirham                                              23.0367

Canadian Dollar                                       86.4971

Swiss Francs                                            90.0162

JPY(100)                                                 108.2463

SW Kroner                                               12.8098

NOR Kroner                                            14.7146

DAN Kroner                                            14.5971

IND Rupee                                               1.5516

Hongkong Dollar                                     10.9119

Saudi Riyal                                              22.5626

Chinese Yuan                                          13.3844

Australian Dollar                                     87.9535

 

              Note:  Applicable CBK mean rates for KenGen power plants with Kenya Shillings denominated charge rates are as stipulated in the respective Power Purchase Agreements.              

 

G=             Total of all Units purchased by the Company from Electric Power Producer(s), generated by the Company and net imports during the calendar month immediately preceding each meter reading period, including all hydro stations, Off-Grid power stations and imports.

L =           Target System loss factor in transmission and distribution equal to 16.8% in year 2013/14, 16.6% in year 2014/15 and 15.9% in year 2015/16.

 

(a)       The Company shall publish a monthly notice in the Kenya Gazette showing the amount of the Foreign Exchange Rate Fluctuation Adjustment applicable to all Unit charges specified in Part II of the Schedule of Tariffs for all meter readings taken during the month of publication of the said notice.

 

(i)         Inflation Adjustment

 

(a)      All units billed to each Post-paid Consumer or purchased by each Pre-paid Consumer every month shall be liable to an Automatic adjustment for inflation at the end of every six month period starting from 1st January, 2014.

 

The effect of domestic and international inflation on cost of supply shall be calculated in accordance with the following formula:

 

INFAt =                          ×      (                                                                      )      ×100

 

Where;

 

INFAt =   Total Inflation Adjustment in Kenya cents per Unit for the half year period t. The first adjustment shall be effected on 1st January 2014.

 

L     =       Target System loss factor in transmission and distribution equal to 16.8% in year 2013/14, 16.6% in year 2014/15 and 15.9% in year 2015/16.

 

Gp =        Total projected Units generated or purchased by the Company from Electric Power Producer(s), during the half-year Adjustment Period.  This shall also include other power plants to be constructed and in respect of which the Company shall enter into a Power Purchase Agreement.

 

INFAKenGen

 

INFAKenGen =

 

Where;

INFAKPi=                 Specific Inflation Adjustment in half-year period, relating to contracted  KenGen Plant i, which shall be determined as follows:

 

 

 

 

 

Where:

KPi           =          Contracted capacity for KenGen Plant i in kW.

 

FOMCR bi=       The base Escalable Capacity Charge Rate for KenGen Plant i in KSh/kW/year for September 2012, divided by two

 

VOMCR bi  =            The base escalable  Variable Operation and Maintenance Charge Rate or variable energy charge rate as applicable, for KenGen plant i in KSh/kWh for September, 2012.

 

Gki=                        Projected Units purchased from KenGen plant i in kWh in the half-year Adjustment Period.

 

CPIUb =                  The Geometric Underlying Consumer Price Index for September 2012 as posted by Kenya National Bureau of Statistics (Index base – February 2009 = 100), being 126.15.

 

CPIUt =                   The Underlying Consumer Price Index for the month of March for adjustments effected in the period July – December; and September for adjustments effected in the period January – June every year as provided by the Kenya National Bureau of Statistics (Index base – February 2009 = 100).

 

USCPIb =                The “Consumer Prices Index for all urban consumers (CPI - U) for the US city average for all items 1982 - 84 =100" as published by the United States Department of Labour Statistics index for September 2012, being 231.407.

 

USCPIt =                 The “Consumer Prices Index for all urban consumers (CPI - U) for the US city average for all items 1982 - 84 =100" as published by the United States Department of Labour Statistics index for the month of March for adjustments effected in the period July – December; and for September for adjustments effected in the period January – June every year.

 

i)                   INFAIPP

 

INFA IPP=

 

Where,

 

INFAIPPi=              Specific Inflation Adjustment in half-year period, relating to contracted  Electric Power Producer’s (excluding KenGen) Plant i, which shall be determined as follows:

 

 

                                                                                                                                           *

 

Where:

 

IPPi          = Contracted capacity for IPP Plant i in kW.

 

CCRbi      = Base escalable capacity charge rate for IPP plant i in US$/kW/year, for September 2012, divided by two.

 

GIPPi         = Projected Units purchased from IPP plant i in kWh in the half-year Adjustment Period.

 

ECRbi     = Base escalable energy charge rate for IPP plant i in US$/kWh for September 2012.

 

USCPIb  = The “Consumer Prices Index for all urban consumers (CPI - U) for the US city average for all items 1982 - 84 =100" as published by the United States Department of Labour Statistics index for September 2012, being  231.407.

 

USCPIt  = The “Consumer Prices Index for all urban consumers (CPI - U) for the US city average for all items 1982 - 84 =100" as published by the United States Department of Labour Statistics index for the month of March for adjustments effected in the period July – December; and for September for adjustments effected in the period January – June every year.

                *Note:

For Euro denominated costs

 

CCRbi =  Base escalable capacity charge rate for IPP plant i in  €/kW/year, for September 2012, divided by two.

 

ECRbi=   Base escalable energy charge rate for IPP plant i in €/kWh    for September 2012.

 

USCPIb=   The Monetary Union Index of Consumer Prices for European Union as published by Eurostat for September 2012 being 116.44.

 

USCPIt=    The Monetary Union Index of Consumer Prices for European Union as published by Eurostat for the month of March for adjustments effected in the period July-December; and for September for adjustment effected in the period January-June every year.

 

All inflation adjustment costs for IPPs shall be converted to Kenya Shillings using the base exchange rates in this Schedule of Tariffs and Rates 2013.

 

ii)            INFAKPLC

 

     INFAKPLC      Is the Specific Inflation Adjustment in half-year period, relating to the Company’s transmission and distribution operation and maintenance costs, which shall be determined as follows:

 

 

 

 

 

Where;

 

TDOM b =             The transmission and distribution network operation and maintenance costs excluding depreciation of assets and provision for bad debts in year2011/12, divided by two.

CPIUb =                   The Geometric Underlying Consumer Price Index for September 2012 as posted by Kenya National Bureau of Statistics (Index base – February 2009 = 100), being 126.15.

 

CPIUt =                    The Underlying Consumer Price Index for the month of March for adjustments effected in the period July – December; and September for adjustments effected in the period January – June every year as provided by the Kenya National Bureau of Statistics (Index base – February 2009 = 100).

 

USCPIb =                 The “Consumer Prices Index for all urban consumers (CPI - U) for the US city average for all items 1982 - 84 =100" as published by the United States Department of Labour Statistics index for September 2012, being 231.407.

 

USCPIt =                  The “Consumer Prices Index for all urban consumers (CPI - U) for the US city average for all items 1982 - 84 =100" as published by the United States Department of Labour Statistics index for the month of March for adjustments effected in the period July – December; and for September for adjustments effected in the period January – June every year.

Note:

                   Any difference between the total inflation costs and the actual billed amount for a given half year adjustment period shall be adjusted for in the following half year period.

 

(b)       The Company shall publish in the first month of the half-year inflation adjustment period a notice in the Kenya Gazette showing the half-year Inflation Adjustment rate applicable to all Units billed to each Post Paid Consumer or with respect to Pre-paid Consumer Units sold during that half-year period.

 

(ii)                 Security Support Facility

 

a) All units billed to each Post-paid Consumer or purchased by each Pre-paid Consumer shall with effect from the last day of the month in which Lake Turkana Wind Power Limited (LTWP) commissions into operation at least 50MW of the 300MW Wind Power Plant under the Power Purchase Agreement between the Kenya Power & Lighting Company Limited (KPLC) and LTWP, be liable to security support facility monthly computed in accordance with the Formula set out below this paragraph 4.  The security support facility shall be collected and remitted by KPLC into an escrow account established as security for the KPLC’s payment obligations to Lake Turkana Wind Power Limited under the Power Purchase Agreement in respect of the 300MW Wind which has been approved by the Commission.  The security support facility hereby shall be charged  on all units consumed monthly in accordance with this paragraph until  the total amount in the escrow account is equal to Euro forty two million and six hundred thousand (€ 42,600,000.00) and shall thereafter be discontinued. 

 

The security support facility is calculated in equivalent Kenya cents per unit to the nearest one cent as follows:

               

              =                       × (                                        ) ×100

 

 

Where:

G= Total of all Units purchased by the Company from Electric Power Producer(s), generated by the Company and net imports during the calendar month immediately preceding each meter reading period, including all hydro stations, Off-Grid power stations and imports

 

Gpi = Actual Units purchased by the company from  Lake Turkana Wind Power Limited’s wind power  plant during the calendar month preceding each Post-paid Billing Period or Pre-paid Units Purchase Period.

 

SSFRpi = Euro cents 1.86/kWh

               

 

         = CBK mean exchange rate for the calendar month immediately preceding current Post-paid Billing Period or Pre-paid Units Purchase Period

 

L     = Target System loss factor in transmission and distribution equal to

 16.8% in year 2013/14, 16.6% in year 2014/15 and 15.9% in year 2015/16.

Note

Any difference between the total Security Support Facility and the actual collected amount for a given Post-paid Billing Period or Pre-paid Units Purchase Period shall be adjusted for in the following period.

 

b) The Company shall publish a monthly notice in the Kenya Gazette showing the amount of the Security Support Facility applicable to all units billed or to be billed to Post Paid Consumers during the month of publication of the said notice. The notice shall also show the amount collected by KPLC by way of the security support facility and standing to the credit of the escrow account on the last business day of the month preceding the date of the notice.

 

(iii)                Water Levy

  1.  All units billed to each Post-paid Consumer or purchased by each Pre-paid Consumer every month shall be liable to Water Resource Management Authority (WRMA) Levy for water used by hydro power plants that have a capacity equal to or above 1MW as approved by the Commission.

 

WRMA levy is calculated in Kenya cents/Unit to the nearest one cent as follows:

 

 

                              =                × (                              ) ×100

               Where:

G=      Total of all Units purchased by the Company from Electric Power Producer(s), generated by the Company and net imports during the calendar month immediately preceding each meter reading period, including all hydro stations, Off-Grid power stations and imports

 

Gh = total units purchased from the preceding month from an electric power producer/producers hydro power from plant i that have a capacity equal to or above 1MW, where i  is equal to 1,2,….n during the calendar month preceding each Post-paid Billing Period or Pre-paid Units Purchase Period for plants in the interconnected system or off grid system as the case may be. This shall also include hydro power plants to be constructed and in respect of which the Company shall enter into Power Purchase Agreements.

 

WL = Approved water levy for plant i as per the approved PPA.

 

L     = Target System loss factor in transmission and distribution equal to

 16.8% in year 2013/14, 16.6% in year 2014/15 and 15.9% in year 2015/16.

 

 Note:

Any difference between the total WRMA levy invoiced and the actual collected amount for a given Post-paid Billing Period or Pre-paid Units Purchase Period shall be adjusted for in subsequent periods.

 

b) The Company shall publish a monthly notice in the Kenya Gazette showing the amount of the WRMA Levy applicable to all Unit charges specified in Part II of the Schedule of Tariffs for all meter readings taken during the month of publication of such notice.

 

(iv)                Taxes and Levies

The Consumer shall pay any taxes, levies or duties imposed from time to time by the Government.  At present, the following are levied by the Government-

(i)       VAT at 16% charged to:

  1. Fixed Charge;
  2. Demand Charge;
  3. Foreign Exchange Fluctuation Adjustment;
  4. Fuel Cost Charge; and
  5. Taxable value of electrical energy consumed in a manner required by the Government.

(ii)     Rural Electrification Programme (REP) levy at 5% of revenue from Unit sales.

(iii)   Energy Regulatory Commission (ERC) levy at 3 Kenya cents/kWh.

 

PART IV -OTHER IMPORTANT CONDITIONS

 

1. In the event of the supply of electrical energy to the installation of any Consumer having a Power Factor of less than 0.90, then the Company may give to such Consumer thirty days’ notice in writing requiring him to improve the Power Factor of his installation to or in excess of 0.90.

 

  1. If a Consumer fails to comply with such notice as aforesaid, then the Company shall be at liberty to impose a surcharge as specified below until such time as the Power Factor of such Consumer’s installation is equal, or in excess of 0.90 -

 

(a)      for Consumers charged under Methods DC, SC, SL and IT, the payment for electrical energy consumed in each Post-paid Billing Period (exclusive of VAT, Fuel Cost Charge, Foreign Exchange Rate Fluctuation Adjustment, REP and ERC levies) shall be increased by 2 per cent for each complete 1 per cent by which the power factor is below 0.90; or

 

(b)     for Consumers charged under Methods CI - the payment for electrical energy consumed and chargeable KVA of Demand in each Post-paid Billing Period (exclusive of VAT, Fuel Cost Charge, Foreign Exchange Rate Fluctuation Adjustment, REP and ERC levies) shall be increased by 2 per cent for each complete 1 per cent by which the Power Factor is below 0.90.

 

3. Any apparatus installed by the Company for the purpose of ascertaining the power factor of any Consumer's installation or of any part thereof shall be installed and maintained at the sole expense of the Company.

 

4. The Company shall determine the voltage at which a supply of electrical energy shall be provided to any Consumer’s supply terminals and this voltage shall be maintained by the Company subject to the permissible variations as provided for in the Act.

 

Dated the11th December, 2013.

Frederick Nyang,

Ag. Director General,

Energy Regulatory Commission.           