Pius & 2 others v China Communication Company & another (Environment & Land Case 002 of 2021) [2023] KEELC 17381 (KLR) (15 May 2023) (Ruling)
Neutral citation:
[2023] KEELC 17381 (KLR)
Republic of Kenya
Environment & Land Case 002 of 2021
PM Njoroge, J
May 15, 2023
Between
Kamais Pius
1st Applicant
Guyo Wako
2nd Applicant
Shinda Boru
3rd Applicant
and
China Communication Company
1st Respondent
Kenya National Highway Authority
2nd Respondent
Ruling
1.This application is dated the 12th day of May, 2021 and seeks orders that: -a.The Honourable Court be pleased to order that the proposed Interested Parties be joined in the suit.b.The costs of this application be provided for.
2.On 15/5/2023, all the opposite parties told the court that they were not opposed to the Interested Parties being enjoined in the suit.
3.In the circumstances, the following orders are issued:a. The Interested Parties are granted leave to join the suit in ELC E001 of 2023 and in ELC E002 of 2023.b. Costs shall be in the cause.
DELIVERED IN OPEN COURT AT ISIOLO THIS 15TH DAY OF MAY, 2023 IN THE PRESENCE OF; -Court assistant: Balozi & RahmaAbdullahi for Interested PartiesKibaara for the 1st defendantMiss Nyasani holding brief for Mugo for the Plaintiff.HON. JUSTICE P.M NJOROGEJUDGE