Omar v Muigai (Miscellaneous Application E005 of 2021) [2022] KEHC 303 (KLR) (Commercial and Tax) (28 April 2022) (Ruling)
Neutral citation:
[2022] KEHC 303 (KLR)
Republic of Kenya
Miscellaneous Application E005 of 2021
WA Okwany, J
April 28, 2022
Between
Fatuma Mohamed Omar
Applicant
and
Edward Ngigi Muigai
Respondent
Ruling
1.The applicant and the respondent herein entered into a lease agreement in which the applicant agreed to pay a deposit of Kshs 5,450,000 and monthly rent of Kshs 150,000. A dispute however arose between the parties, which they referred to arbitration. The arbitrator made a finding in favour of the applicant and published the award on 17th April 2020. The applicant subsequently filed the application dated 23rd February 2021 seeking the following orders;1.THAT the arbitral award dated and delivered at Nairobi on the 17th Day of April 2020 by Dr. Ken Nyaundi (sole arbitrator) between the parties herein be recognized, adopted, enforced as a decree of the court.2.THAT the Court be at liberty to make such further and other orders that as it deems fit to meet the ends of justice and3.THAT cost of this application be borne by the respondent.
2.The application is brought under Section 36 of the Arbitration Act, Order 46 rule 18(1) of the Civil Procedure Rules, Rules 6,9,and 11 of the Arbitration Rules.
3.The application is supported by the applicant’s affidavit and is premised on the following grounds: -1.THAT a dispute emerged between the parties herein concerning a dispute on a lease agreement signed on 16th June 2018.2.THAT the parties failed to amicably resolve the dispute among themselves.3.THAT consequently a Sole Arbitrator was appointed on 24th May 2019 to arbitrate on the matter.4.THAT the Sole Arbitrator, Dr. Ken Nyaundi heard the parties herein and delivered his award on the 17th Day of April 2020 and5.THAT the propriety of the award has never been challenged or otherwise disputed since its delivery.
4.The respondent opposed the application through the Grounds of Opposition dated 28th September 2021 replying affidavit dated 17th November 2021. He avers that the applicant is guilty of non-disclosure for failing to disclose that on 25th January 2021 the Arbitrator issued a supplementary award wherein he acknowledged that there was an error in the computation of the award. He states that the arbitrator did not correct the error citing lack of jurisdiction. He avers that adopting the award as is with the error would amount to unjust enrichment.
5.The application was canvassed by way of written submissions which I have considered. The main issue for determination is whether the applicant has met the conditions set, under the Arbitration Act, for the enforcement of an arbitral award.
6.The applicant maintained that the award should be adopted as it has not been challenged or otherwise set aside since its publication. On its part, the respondent argued that the award should not be adopted in its current state in view of the arbitrator’s acknowledgement of the computation error. The respondent’s case was that adopting the award as it is would amount to the applicant’s unjust enrichment. The respondent urged the court to exercise its discretion and enlarge time within which the award may be corrected.
7.Section 36 of the Arbitration act sets out the legal parameters governing enforcement an adoption of an arbitral award. It provides as follows;
8.In Samura Engineering Limited vs Don-Wood Co Ltd [2014] eKLR it was held: -
9.In the instant case, I find that the applicant has met the preconditions for the enforcement of the award. The onus therefore shifts to the respondent to demonstrate why the award should not be adopted.
10.Section 37 of the Arbitration Act guides the court in determining whether or not it should recognize and enforce an award. The respondent’s case is based on an error in the computation of the award. I have perused the supplementary award dated 25th January 2021 and I note that the Arbitrator observed that: -
11.Section 34 of the Arbitration Act empowers the Arbitral Tribunal to correct any computation, clerical or typographical errors where an application for such correction is made within 30 days after receipt of the award. The respondent did not comply with the provisions of the said section and made his request for amendment outside the stipulated time.
12.In Kenya Oil Company Limited & Another vs Kenya Pipeline Company Limited NRB CA Civil Appeal No. 102 of 2012 [2014] eKLR the Court of Appeal cited, with approval, the following dicta by Steyn LJ., in Geogas S.A vs Trammo Gas Ltd (The "Baleares") 1 Lloyds LR 215: -
13.Further in Anne Mumbi Hinga vs Victoria Njoki Gathara [2009] eKLR the court held that;
14.In view of the foregoing, I note that the respondent has not demonstrated that any of the grounds in Section 37 of the Arbitration Act exist in order to persuade the court to reject the application to recognize and enforce the arbitral award. I find that the respondent’s suggestion that this court should issue an order to extend the time within which to correct the computation errors falls outside the jurisdiction of this court. Moreover, the respondent did not explain why it took him so long to approach the Arbitrator to correct the Award.
15.Consequently, I find that the application dated 23rd February 2021 is merited and I therefore allow it with costs to the applicant.
DATED, SIGNED AND DELIVERED VIRTUALLY AT NAIROBI THIS 28TH DAY OF APRIL 2022.W. A. OKWANYJUDGEIn the presence of: -Mr. Mbaji for the respondent.Mr. Kaaya for Wachira for Applicant.Court Assistant- Sylvia